Quick hits
What moved, in brief.
The site-selection scoreboard just got rewritten around delivery
Area Development's 40th annual corporate survey found electric power availability at scale mattered to 98.5% of executives, with 82.6% rating it 'very important' — the highest intensity of any single factor — while 'site readiness and due-diligence status' leapt from 78% a year earlier to 98.5%. The frame has shifted from 'where is cheapest?' to 'where can we be sure this actually works?', and that reorders every pitch an agency makes.
Area Development: 40th Annual Corporate & 22nd Annual Consultants Survey (Q1 2026)Ireland reopens its grid to data centres — on strict terms
In December 2025 Ireland lifted the effective moratorium on new grid connections for Dublin-area data centres that had held since 2021, but only conditionally: large new loads must bring dispatchable generation or storage matching their demand and meet an 80% renewable requirement, with EirGrid and ESB able to reject unsuitable sites. The practitioner read is portable — where a grid is full, the constraint doesn't stop investment, it relocates it toward regions that have headroom and can prove it.
Pinsent Masons: New Irish data centres must generate power back into national grid, rules regulatorCommunity colleges become the other half of the pitch
The American Association of Community Colleges and General Motors expanded their EmployED initiative to eighteen colleges, pushing early technical training for advanced manufacturing — the talent plumbing behind headline wins like Micron's planned upstate New York fab, paired with SUNY. The lesson for agencies: the second question after 'can you power it?' is 'can you staff it?', and the credible answer is a named training partner with a curriculum, not a labour-force brochure.
Community College Daily: Renewing America's advanced manufacturing workforceASEAN banks a near-record FDI year on the strength of its clusters
Southeast Asia pulled in roughly $225 billion of FDI, up about 10% and its second-highest total on record, concentrated in advanced manufacturing, semiconductors, batteries, data centres and green energy. The pattern holding across a softer global year: capital is consolidating where skills, power and a credible cluster line up — generic openness and low wages no longer clear the bar.
Investment Monitor: FDI in 2026 — regional experts weigh in on future trendsAfrica's FDI number whiplashes — read it by mode
African FDI inflows hit a record $96 billion in 2024, then fell about 38% to roughly $59 billion in 2025 as a handful of very large projects washed through the totals. For agencies and ministers it is the cleanest recent case for stripping out one-off megadeals and reporting flows by mode before briefing a headline a single project can make or unmake.
UNCTAD: Global foreign direct investment falls for the second consecutive yearMegawatts are the new acreage: what a site needs to be 'power-ready' — and why most aren't
The binding constraint on a new plant or data hall has quietly moved from cost to electricity. For a local agency that turns power procurement into an economic-development function — and 'shovel-ready' into a claim you now have to prove.
For thirty years the site-selection conversation ran on cost: land price, wage rates, the incentive package. It doesn't anymore. Area Development's 40th annual corporate survey, out this quarter, found electric power availability at scale mattered to 98.5% of executives, with 82.6% calling it 'very important' — the single highest-intensity score in the entire dataset. Transmission and substation capacity registered at 97%, certainty of permitting at 94%, and 'site readiness and due-diligence status' vaulted from 78% a year earlier to 98.5%, one of the sharpest year-on-year jumps ever recorded in the survey. The question executives now put to their advisers is not 'where is cheapest?' but 'where can we be sure this will actually work?' That is a different scoreboard, and it favours a different kind of place.
The mismatch driving all of this is a timing one. A modern manufacturing box or data hall can be built in twelve to eighteen months. Connecting it to the grid takes years — four to ten across major US markets, and by JLL's 2026 outlook a 100-megawatt connection in a constrained market like Northern Virginia can wait roughly seven. The building is no longer the long pole in the tent; the wire is. When a developer models a project, a five-year delay to energization erodes the internal rate of return and quietly moves capital to a market that can deliver electrons sooner. Time-to-power has become the screen that runs before land, incentives or fibre are even discussed.
This is not only an American story, and reading it globally is what makes the opportunity legible. Ireland ran a de facto moratorium on Dublin-area data-centre connections from 2021 until December 2025, and reopened only on strict terms — dispatchable capacity, an 80% renewable requirement, and grid operators empowered to refuse sites. Amsterdam and much of the Netherlands cap or ban hyperscale builds outright; Denmark paused new connections in 2026 as demand overwhelmed its grid; Singapore replaced its own moratorium with a rationed, efficiency-gated allocation. Everywhere a grid fills up, the same thing happens: the investment doesn't evaporate, it goes looking for headroom. For a region that has spare capacity and can document it, congestion somewhere else is a pipeline.
So what does 'power-ready' actually mean, past the brochure adjective? Not 'there's a substation nearby.' It means a specific deliverable-megawatt figure attached to a date; a utility letter or executed interconnection agreement committing that capacity and timeline; land with clear title and completed environmental and geotechnical due diligence; a permitting path that is mapped and time-bounded rather than aspirational; and, increasingly, an on-site or adjacent generation-and-storage option so the site isn't hostage to the interconnection queue. Powered land trades at a premium for one reason — it collapses the schedule — and the agencies winning large loads are the ones handing an investor those five facts on day one rather than promising to go find them.
That reframes the agency's own job. Power procurement used to be a utility back-office matter; it is now an economic-development function, and it belongs upstream of the prospect, not after it. The work is unglamorous and familiar to anyone who has read this brief on project preparation: sit between the developer and the utility before either has met; pre-negotiate blocks of capacity; co-invest, where the economics justify it, in the substation or transmission upgrade that unlocks a marketed site; and be able to state a credible time-to-power number the moment an inquiry lands. The community that did the engineering study and had the utility conversation last year can answer in a meeting. The one that starts when the RFI arrives has already lost the schedule.
A closing caution, because this is a market where overselling is now expensive. 'Shovel-ready' without an engineering-validated power figure and a real permitting timeline is not a selling point; it is a liability with the exact consultants who screen on time-to-power first and will catch an inflated megawatt claim in due diligence. The communities that win the next decade of energy-intensive investment are not the cheapest. They are the ones that can prove — on paper, with a date, backed by a utility — that the megawatts show up when they say they will.
Approximate timelines to bring a large energy-intensive facility online, in years. A modern data hall or plant is built in 12-18 months; a typical grid interconnection runs four years, and a 100MW connection in a constrained market can take around seven. Sources: JLL 2026 Global Data Center Outlook; industry estimates via Construction Owners and Area Development.
Why it matters for practitioners
- ◆Lead with deliverable power, not land price. Put a specific megawatt figure and a utility-backed energization date at the top of the pitch — that now outranks cost and incentives in the client's screen, so make it the first thing they see.
- ◆Make power procurement an EDO function. Get ahead of prospects: pre-negotiate capacity with your utility, map the substation and transmission upgrades your marketed sites need, and be ready to state a credible time-to-power number on day one rather than after the RFI.
- ◆Prove readiness; never merely assert it. 'Shovel-ready' without an engineering-validated power study and a time-bounded permitting path is a credibility risk with consultants who screen on time-to-power first. A validated number beats a brochure adjective every time.
- ◆What to do this week: build a one-page power dossier for your top marketed site — deliverable MW today, MW with a named upgrade and its in-service date, interconnection status, permitting timeline, and any on-site or adjacent generation option. Any line you can't fill is your readiness gap, and your next capital ask.
Sources
- Area Development: 40th Annual Corporate & 22nd Annual Consultants Site Selection Survey (Q1 2026)
- Environment+Energy Leader: Site Selection Is Now an Energy Access Decision in 2026
- Construction Owners: How long it actually takes to power a data center in 2026 — a market-by-market reality check
- White & Case: DOE directs FERC to accelerate interconnection of data centers
- Lawrence Berkeley National Laboratory: Queued Up — interconnection queue data
- Pinsent Masons: New Irish data centres must generate power back into national grid, rules regulator
- Data Center Dynamics: The ongoing impact of Amsterdam's data center moratorium
- CNBC: Denmark faces data center reckoning as power grid overwhelmed by surging demand
- Community College Daily: Renewing America's advanced manufacturing workforce — a community college imperative
- Investment Monitor: FDI in 2026 — regional experts weigh in on future trends
- UNCTAD: Global foreign direct investment falls for the second consecutive year
Get the Brief in your inbox
Free. Each issue, the day it publishes.