Quick hits
What moved, in brief.
UNCTAD put strategic sectors at 44% of greenfield project value and the poorest economies at a tenth of it
UN Trade and Development published World Investment Report 2026 on July 7, 2026. It records global foreign direct investment rising 6% to $1.6 trillion in 2025, with inflows to developed economies up 11% against 2% growth in developing economies, which reached $901 billion. The concentration is the part that changes a promotion pitch: strategic sectors, meaning AI infrastructure, semiconductors, critical minerals and energy transition technologies, took 44% of global greenfield project values in 2025, up from 16% in 2020, and the top 20 host economies took more than 80% of all FDI. Low-income and lower-middle-income economies attracted about 10% of strategic-sector investment between 2020 and 2025, against more than 20% in other sectors. The Doyen Report on the capture gap sets out how to measure what a place keeps from a project of that kind.
Global investment rises 6% to $1.6 trillion, but development gains remain unevenKOTRA is running its Southeast Asia export push through 11 overseas offices and 160 companies
The Korea Trade-Investment Promotion Agency said on August 4, 2026 that its 2026 Export Market Expansion project for Southeast Asia runs from July to August with 160 Korean companies enrolled. The package is webinars, one-to-one video consultations arranged through 11 trade offices in markets including Vietnam, Singapore, Thailand and Indonesia, and marketing content produced at 20 AI trade support centers inside Korea. Korean exports to ASEAN rose 53% year on year in the first half of 2026 to $88.2 billion, consumer goods exports to the bloc reached $3.2 billion, up 8%, and two of the seminars are aimed at Indonesia's mandatory halal certification, which takes effect in October.
KOTRA Backs Consumer Goods, Halal Exporters Targeting Southeast AsiaMAN Truck & Bus is doubling its Krakow plant and making it the group's second electric truck site
Site Selection reported on August 3, 2026 that Germany-based MAN Truck & Bus will spend $1.3 billion expanding its Krakow production site, adding a body-in-white and paint shop, facilities for painted truck bodies and more cab assembly. The work doubles the plant's production area to over 2.9 million sq. ft. and makes Krakow the company's second plant building electrified trucks. Chief executive Alexander Vlaskamp tied the decision to the MAN2030 program and to the start of series production of the company's electric light-duty range.
Project Bulletin, August 3, 2026: Kraków, Poland; Rock Hill, South Carolina; El Paso, TexasOctapharma named four reasons for Rock Hill, and none of them is an incentive
The plasma products company Octapharma will invest $1.5 billion on a 50-acre site at Palmetto Research Park in Rock Hill, South Carolina, its first manufacturing plant in the United States and, Site Selection reported on August 3, 2026, the largest private biomedical investment in the state's history. The project creates 1,500 direct jobs. The company said it selected South Carolina for advanced manufacturing infrastructure, deep-water port access, talent and proximity to major logistics networks, and chairman and chief executive Wolfgang Marguerre framed domestic supply of the company's therapies as a national security question.
Project Bulletin, August 3, 2026: Kraków, Poland; Rock Hill, South Carolina; El Paso, TexasThe African Development Bank put Southern Africa's annual financing gap at $55 billion by 2030
The African Development Bank released its 2026 Regional Economic Outlook for Southern Africa on July 29, 2026. It projects regional growth of 2.1% in 2026 rising to 2.7% in 2027, and puts gross capital formation at around 18.6% of GDP by 2025, below the level the Bank says middle-income economies need for structural transformation. Kennedy Mbekeani, the Bank's Director General for Southern Africa, said the problem is not a shortage of money but "mobilising, intermediating, and deploying the capital that already exists, effectively and at scale." The report names diaspora remittances in Lesotho and Zimbabwe and pension assets in Namibia and South Africa as the pools going unused.
Regional Economic Outlook 2026: Southern Africa Must Mobilise Development Finance at Scale to Close Annual $55 Billion Financing GapThe federal fix for large loads begins at 50 MW, and the projects below that line stay with the state
FERC's six orders reach the largest loads in six markets, and the biggest queue in the country sits in Texas, outside its jurisdiction and paused.
On June 18, 2026, the Federal Energy Regulatory Commission gave PJM, MISO, SPP, CAISO, ISO New England and NYISO 60 days to defend or rewrite the tariff rules governing how large electricity users connect to the transmission grid. The filings land on Monday, August 17, in six dockets numbered EL26-67 through EL26-72.
The definition FERC wrote is where an economic development officer should start reading. Under the show cause orders, a large load is a single-site commercial or industrial customer, not part of a co-location arrangement, with a peak load of 50 MW or more interconnecting at a voltage above 69 kV. The Department of Energy had proposed a lower bar. Its advance notice of proposed rulemaking, submitted to FERC on October 23, 2025, framed the problem around facilities of 20 MW or greater and recommended assigning 100% of network upgrade costs to the interconnecting load. FERC kept the cost principle and raised the threshold. The band between 20 MW and 50 MW, which covers most food processing, battery assembly and mid-size fabrication work, sits outside the federal remedy and stays with a state commission and a utility.
So the August 17 filings are a cost-allocation event before they are a speed event. FERC directed each grid operator to produce a standard cost recovery agreement, signed by the operator, the transmission owner and the customer, requiring the customer to make a minimum contribution to the transmission owner's revenue requirement backed by credit support. It told the operators a large-load study should take no more than 60 to 90 days. It also directed them to require hourly load forecasts, real-time telemetry, ramp rate and ride-through terms, phasor measurement units and remote disconnect capability, all at the customer's expense. A site that clears the threshold gets a clock and a price. A site below it gets neither.
Texas moved the other way in the same fortnight. On August 3, 2026, Governor Greg Abbott wrote to the Public Utility Commission of Texas and ERCOT calling for an audit of every data center in the interconnection queue, noting that requests total about 474 GW, which he said is more than five times the state's record peak demand, and that data centers make up about 90% of the new requests. ERCOT delayed its Batch Zero transmission planning study, the first set of projects to run through the state's new large load process, and said it will ask the commission for a good-cause exemption at its August 20 open meeting. ERCOT is not FERC-jurisdictional, so nothing filed on August 17 governs a Texas site. New York halted new data center approvals for up to a year in July. In the same week the audit was ordered, Meta Platforms and BlackRock announced a $14 billion, 1 GW campus in El Paso, due online in 2028 with 300 direct jobs and BlackRock holding 80% of it.
The strongest objection is that a tariff is not a megawatt. The North American Electric Reliability Corporation, in the Long-Term Reliability Assessment it published on January 29, 2026, forecast summer peak demand on the bulk power system growing by 224 GW over the following decade, 69% above the 132 GW it projected a year earlier, with winter growth of 246 GW against 149 GW. It placed MISO, PJM, ERCOT and parts of the Pacific Northwest at high risk of insufficient reserve margins within five years. On that evidence a faster study reorders a queue without adding supply, and the binding constraint stays generation and transmission construction. That objection is correct, and it narrows the claim rather than defeating it. What changes on August 17 is not how much power exists. It is what a developer is told the connection will cost, how soon, and who carries the upgrade.
The claim is testable inside the year. If the six operators mostly argue that their existing tariffs are already just and reasonable and FERC accepts those defenses, the federal cost terms will not move and the question returns entirely to state commissions and utilities; parties have 30 days after the filings to comment. FERC also limited the six orders to the RTOs it regulates and left its rulemaking docket, RM26-4, open for action in non-RTO regions. A site in ERCOT, in most of the Southeast, or in the non-RTO West is governed by nothing that gets filed on Monday. ERCOT's request for more time goes to the Public Utility Commission of Texas on August 20.
Projected growth in bulk power system peak demand over the decade following each assessment. Source: North American Electric Reliability Corporation, Long-Term Reliability Assessment published January 29, 2026, compared with its 2024 edition, as reported by Utility Dive on January 30, 2026.
Why it matters for practitioners
- ◆Sort your live pipeline by peak load this week. A project at 50 MW or more interconnecting above 69 kV falls inside FERC's definition and inside whatever the grid operators file on August 17. Anything under 50 MW stays with your state commission and your utility, on a different clock and a different cost rule.
- ◆Read the cost recovery agreement before you read the study timeline. FERC directed a minimum customer contribution to the transmission owner's revenue requirement, secured by credit support, which changes the capital a tenant posts before construction starts and belongs in the term sheet rather than a footnote.
- ◆Ask your transmission owner for the generation adequacy report it filed on July 18. FERC required one from every grid operator and transmission owner within 30 days of the June 18 orders, and it is the clearest public statement of whether the power behind your site exists.
- ◆If you market sites in ERCOT, assemble three answers for every prospect now: on-site generation, water sourcing and reuse, and what state or local financial assistance the project has taken. Those are the headings in Abbott's audit, and he wrote that a project failing it must be denied.
Sources
- FERC Launches Aggressive Targeted Action to Speed Large Load Integration
- FERC orders grid operators to promptly revise or justify interconnection rules for data centers and large loads
- Interconnection of Large Loads to the Interstate Transmission System (Docket No. RM26-4-000)
- Facing an estimated 474 GW of interconnection requests, Texas hits pause on data centers
- NERC forecasts peak demand to rise 24% on new data center loads
- Global investment rises 6% to $1.6 trillion, but development gains remain uneven
- KOTRA Backs Consumer Goods, Halal Exporters Targeting Southeast Asia
- Project Bulletin, August 3, 2026: Kraków, Poland; Rock Hill, South Carolina; El Paso, Texas
- Regional Economic Outlook 2026: Southern Africa Must Mobilise Development Finance at Scale to Close Annual $55 Billion Financing Gap
Get the Brief in your inbox
Each issue is free and arrives the day it publishes.